Financial Number: 447661-1-52-01
Project Length: 4.883 Miles
Project Limits: State Road (SR) A1A/North Ocean Drive from SE 31 Street to South of Grand Court
Project Purpose: The Resurfacing, Restoration and Rehabilitation (RRR) project will extend the service life of the pavement, enhance roadway safety, improve connectivity to transit, and improve operating characteristics of the corridor.
Public Meeting: Wednesday, November 15, 2023, at 6:00 p.m. and will be offered in-person and virtually simultaneously.
The public meeting will take place at the Boca Raton Public Library located at 400 NW 2 Avenue, Boca Raton, FL 33432.
To participate in the virtually from your computer, tablet or smartphone please register using the following link:https://attendee.gotowebinar.com/register/5783196296518822748
Participants can also use their phone by dialing in to+1 (415) 930-5229; Access Code: 300-041-221
The public meeting will consist of a formal presentation followed by an open discussion. Staff will be available to answer questions and provide assistance. Comments and questions will be answered in the order received.
If your question is not answered during the event, a response will be provided in writing following the meeting. Questions and comments may also be submitted prior to the meeting by e-mailing the Project Manager.
Start Date: Fall 2027
Completion Date: Fall 2028
Estimated Construction Cost: $7.3 million
Scope of Work:
- Milling and resurfacing of the existing travel lanes, shoulders, and adjacent asphalt path to preserve the pavement service life
- Narrowing the existing travel lanes from 12-feet to 11-feet, and widening existing paved shoulders less than 4-feet, to provide a continuous 6-foot bicycle facility to improve safety for bicyclists
- Increasing the width of the two-way left turn lane from 10-feet to 11-feet by reducing the adjacent travel lanes from 11.5-feet to 11-feet (5-foot bicycle lanes will be provided where the two-way left turn lane is present)
- Updating deficient curb ramps/detectable warning surfaces to comply with ADA and installing a new sidewalk along the east side from the beginning of the project to the intersection of Camino Real to facilitate safety for pedestrians with disabilities
- Improving access to bus stops and adding landing pads where missing to improve connectivity to transit
- Adding new signalization and lighting at the intersections of Camino Real and Spanish River Boulevard to improve the visibility of pedestrians and bicyclists for drivers at the intersection
- Replacing corridor-wide substandard signing and pavement markings
- Replacement of existing French drain exfiltration systems in front of the Marbella Condominium at 250 S Ocean Boulevard to eliminate localized flooding on both sides of SR A1A
- Replacing deficient guardrail sections to improve their crash shielding capabilities
Construction Impacts:
- Work will be done in phases to reduce the effects of construction on the community
- No construction will be allowed during weekends
- Access to properties adjacent to the corridor will be maintained throughout construction
- Pedestrian and bicyclist detours will be provided to maintain access through the work zone
Point of Contact:
Project Map:
|