Financial Number: 439845-1-52-01
Project Length: 2.04 Miles
Project Limits: State Road (SR) 715 from north of State Road (SR) 80 to south of West Canal Street South
Public Meeting: Thursday, September 1, 2022, at 5:00 p.m.
Start Date: Summer 2023
Completion Date: Summer 2024
Estimated Construction Cost: $6 million
Scope of Work:
- Repaving the existing roadway
- Shoulder widening to provide 7-foot buffered bike lanes
- American with Disabilities Act (ADA) sidewalk curb ramp improvements
- Signing and pavement marking improvements
- Adding 6-foot wide sidewalk on west side of State Road 715
- Adding new roadway lighting, signalization improvements and replacing deficient guardrail segments
Construction Impacts:
- Work will be performed in phases to reduce the impacts to the community
- Access to businesses and residences will be maintained at all times during construction
- Temporary lane closures during off-peak hours will be required