Financial Number: 446100-1-52-01
Project Length: 2.35 Miles
Project Limits: State Road (SR) 80 from State Road (SR) 25/US 27 to east of Glades Glen Drive
Public Meeting: Thursday, September 1, 2022, at 5:00 p.m.
The Public Meeting will be offered in two different formats: virtual and in-person.
To participate in the virtual public meeting from your computer, tablet or smartphone please register using the link below:
https://register.gotowebinar.com/register/3755167983659397391 Participants can also use their phone by dialing in to +1 (631) 992-3221; Access code: 212-291-971.
The in-person public meeting will take place at the City of Belle Glade City Hall located at 110 Doctor Martin Luther King Junior Boulevard West, Belle Glade, Florida 33430. The latest social distancing guidelines will be followed.
Start Date: Summer 2023
Completion Date: Summer 2024
Estimated Construction Cost: $5.3 million
Scope of Work:
- Repaving the existing roadway
- Shoulder widening to provide 7-foot buffered bike lanes
- American with Disabilities Act (ADA) sidewalk curb ramp improvements
- Signing and pavement marking improvements
Construction Impacts:
- Work will be performed in phases to reduce the impacts to the community
- Access to businesses and residences will be maintained at all times during construction
- Temporary lane closures during off-peak hours will be required
Contact Information:
|