SR 5/US 1 Feasibility Study/Preliminary Design

Financial Number: 438386-2-32-01

Project Length: 3.065 miles

Project Limits: SR 5/US 1 from 59th Street to SR 850/Northlake Boulevard

Projected Letting: July 5, 2024

Start Date: Fall 2024 (construction)

Completion Date: Spring 2025

Estimated Construction Cost: $5.8 M

Scope of Work:

  • Construction of new raised median from Silver Beach Road to Palmetto Drive.

Construction Impacts:

  • One lane will remain open at all times during construction.
  • Daytime non-peak hours: 9:00 a.m.to 4:00 p.m. Monday through Friday.
  • Nighttime non-peak hours: 9:00 p.m. to 5:30 a.m. Sunday through Thursday.
  • All work is to be done in phases to reduce impacts of construction to the community.

Contact Information:

 
 
 
Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone
zero