Financial Number: 447670-1-52-01
Project Lengths: 3.403 miles
Project Limits: SR 7/US 441 from north of SR 808/Glades Road to north of Bridgebrook Drive
Virtual Public Meeting: Tuesday, July 15, 2025, from 5:00 p.m. to 6:00 p.m. Please use the following link to register: https://tinyurl.com/SR7GladestoBridgebrook. You may also call +1 (562) 247-8422, Access Code: 600-365-065.
In-Person Construction Open House: Tuesday, July 15, 2025, from 6:00 p.m. to 7:00 p.m. at the West Boca Library — Large Conference Room, located at 18685 FL-7, Boca Raton, FL 33498
Start Date: July 8, 2025
Completion Date: Late 2026
Contractor: Weekley Asphalt Paving, Inc.
Construction Cost: $9.5 million
Scope of Work: The project improvements consist of milling and repaving the existing roadway throughout the project limits to enhance infrastructure resilience and improve safety for the community; restriping the roadway to provide seven-foot-wide bicycle lanes throughout the project limits to enhance cyclist safety; constructing a new six-foot-wide sidewalk along the east side of SR 7/US 441 from the West Boca Plaza to Kimberly Boulevard to enhance pedestrian accessibility; upgrading curb ramps and replacing sections of the existing sidewalk to enhance safety and connectivity for pedestrians; upgrading pedestrian signals with new LED countdown timers at Kimberly Boulevard, New England Boulevard, CR 794/Yamato Road, Boca Chase Drive/Boca Gardens Parkway, and Clint Moore Road to enhance pedestrian accessibility; upgrading lighting for pedestrian crosswalks at all signalized intersections for pedestrian and motorist safety; upgrading signage and pavement markings, including installing green bicycle markings at right turn lanes,
to enhance visibility and safety.
Documents:
447670-1 SR 7 Glades to Bridgebrook Project Flyer.pdf
Point of Contact:
Para información y preguntas en Español, por favor llame al (954) 777-4302.
|