Financial Number: 446374-1-52-01
Project Length: 14.828 miles
Project Limits: State Road (SR) SR 700/Conners Highway from north of 1st Street to west of SR 80
Start Date: May 1, 2024
Completion Date: Early 2026
Contractor: General Asphalt Company
Estimated Construction Cost: $17.8 million
Scope of Work: Project improvements include milling and resurfacing of SR 700/Conners Highway, replacing and upgrading existing curb ramps to meet Americans with Disabilities Act (ADA) standards, installing rumble strips for the roadway segment with a posted speed greater than 50 miles per hour (mph), minor shoulder widening in various locations, installing, upgrading, and repairing guardrail as needed, upgrading pedestrian signals, pavement markings and signs.
Point of Contact:
Para información y preguntas en Español, por favor llame al (954) 777-4302.
Documents:
FULL CLOSURE SR 700_Oct 21 2024 through May 18 2025
FULL CLOSURE SR 700_May 1 to Sept 30 2024
|