SR 794/Yamato Road Resurfacing, Restoration, and Rehabilitation (RRR) Project
Financial Numbers: 447657-1-52-01
Project Lengths: 0.633 miles
Project Limits: SR 794/Yamato Road from east of SR 9/I-95 to SR 5/US 1/Federal Highway
Start Date: February 2025
Completion Date: Spring 2026
Contractor: General Asphalt Co. LLC
Construction Cost: $3.5 million
Scope of Work:
The project improvements consist of milling and repaving the existing roadway within the project limits to enhance long-term infrastructure resiliency; upgrading curb ramps and replacing select sidewalk sections of the existing sidewalk to enhance pedestrian safety; replacing traffic signal mast arms at NW 2nd Avenue to improve infrastructure resiliency and motorist safety; upgrading roadway lighting and installing new LED countdown pedestrian signal heads at NW 2nd Avenue and Dixie Highway to improve pedestrian safety at crosswalks; and upgrading signage and pavement markings to enhance visibility and motorist safety.