Financial Number: 433888-1-52-01
Project Length: 0.2-miles
Project Limits: Blue Heron Boulevard Bridge over the Intracoastal Waterway, Riviera Beach
Start Date: July 12, 2019
Completion Date: July 15, 2020
Contractor: M&J Construction
Estimated Construction Cost: $1.6 million
Scope of Work: Work included removing and replacing the bridge fender and navigational lighting systems and removing all platforms and ladders from the bridge.