Financial Number: 446176-1-52-01
Project Length: 1.835 Miles
Project Limits:
- SR A1A from S John D MacArthur Entrance to Portage Landing North
Virtual Public Meeting:
- Date: Thursday, May 18, 2023, at 6:00 p.m.
In-Person Public Meeting:
- Date: Wednesday May 24, 2023, at 6:00 p.m.
- In-Person Location: North Palm Beach Library, 303 Anchorage Drive, Obert Community Room, North Palm Beach, FL 33408
Projected Letting: 02/02/2024
Start Date: Spring 2024
Completion Date: Summer 2025
Estimated Construction Cost: $2.6 Million
Scope of Work:
- Repaving and restriping the existing roadway
- Widen shoulders 3-foot to provide 8-foot paved shoulders
- Reconstructing pedestrian sidewalk curb ramps
- Upgrading pedestrian signalization at the intersection of Lost Tree Village/Old Harbour Road
- Replacing existing signal and wood strain poles to mast arms
- Replacing and upgrading of signage impacted by construction
- Lighting retrofits at the signalized intersection of Lost Tree Village/Old Harbour Road
Construction Impacts:
- Work will be done in phases to reduce the inconvenience to the community
- Lane closures will occur during non-peak hours to minimize impacts on traffic
- Access to residents and businesses will be maintained at all times during construction