State Road (SR) 5/Federal Highway Resurfacing, Restoration and Rehabilitation (RRR) Project

Financial Number: 447660-1-52-01

Project Length: 1.58 miles

Project Limits: From 6 Avenue N. to Arlington Road

Virtual Public Workshop:

Construction Start Date: Early 2025

Anticipated Completion Date: Summer 2026

Estimated Construction Cost: $1.6 million

Scope of Work:

  • Repave the existing roadway
  • Upgrade curb ramps to comply with the Americans with Disabilities Act (ADA)
  • Upgrade pedestrian signals at 7 Avenue N., 10 Avenue N., and 13 Avenue N. to countdown signals
  • Install Rectangular Rapid Flashing Beacons (RRFBs) and crosswalks at the north side of 6 Avenue N. (Link for more information)
  • Install raised intersection at 16 Avenue N. (Link for more information)
  • Install speed feedback signs near the curves at Wellesley Drive
  • Upgrade signage and pavement markings

Construction Impacts:

  • Work will be done in phases to reduce the impacts to the community
  • Temporary lane closures will be required
  • Pedestrian traffic will be maintained
  • Access to properties along the corridor will be maintained at all times

Public Notice: The design public meeting is scheduled for Thursday, July 13, 2023, at 5:30 p.m. and will be offered in-person and virtually.

In-Person: The meeting will take place at the City of Lake Worth Beach City Hall at 7 N. Dixie Highway, Lake Worth Beach, FL 33460 and consist of a formal presentation followed by an open discussion.

Virtual Public Meeting: To participate virtually from your computer, tablet or smartphone please register using the following link: https://bit.ly/SR5-6AveN-ArlingtonRd-Meeting. Participants can also use their phone by dialing in to +1 (562) 247-8422; Access code: 767-867-434.

Contact Information:

Documents:

PDF IconSR5 - 6 Ave N to Arlington Rd

Project Location Map



 

Project Photos

Pre-Construction

Click to view enlarged version/details

 

Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone