State Road (SR) 786/PGA Boulevard Resurfacing, Restoration, and Rehabilitation Project

Financial Number: 446174-1-52-01

Project Length: 0.922 miles

Project Limits: State Road (SR) 786/PGA Boulevard from east of SR 9/I-95 to east of Fairchild Gardens Avenue

Start Date: October 14, 2024

Completion Date: Spring 2025

Contractor: OHLA USA Inc.

Estimated Construction Cost: $4.9 million

Scope of Work:

Project improvements consist of milling and repaving the existing roadway within project limits to ensure long-term resilience, installing pedestrian signals, pavement markings, and signs to enhance safety for pedestrians and motorists, installing dedicated green bike lane markings in each direction of SR 786/PGA Boulevard throughout the project limits to improve bicyclist safety, installing an advanced warning flasher facing eastbound traffic approaching the Lake Victoria Gardens Avenue signalized intersection to enhance motorist safety, upgrading traffic signal vehicle video detection and traffic controller cabinets to improve traffic flow, reconstructing the concrete bus pad at Fairchild Gardens Avenue to enhance transit rider safety and accessibility, and reconstructing pedestrian sidewalk curb ramps to meet current Americans with Disability Act (ADA) standards.

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

Documents:

PDF IconSR 786 Project Information Flyer.pdf

 

Pre-Construction

Click to view enlarged version/details
IMG_3683 IMG_3668 IMG_3676 IMG_3675
IMG_3664 IMG_3658

During Construction

Click to view enlarged version/details
Signalization Directional Bore Work   October 2024 Signalization Conduit Installation   November 2024 Ped pole Foundation Installation   November 2024 Signalization Pull Box Installation   November 2024
Light Pole Spread Footer Reinforcement   December 2024 Signalization Conduit Trenching and Ped Pole Installation at Fairchilds Gardens   December 2024 Light Pole No. 12 Spread Footer Excavation   December 2024 Light Pole No. 12 Spread Footer   January 2025
Traffic Controller Cabinet Foundation preparation at Lake Victoria Gardens   January 2025 Paver Removal and Asphalt Placed for Stamped Pavers.   February 2025SR 786 PGA Blvd. Palm Beach Gardens Resurfacing   March 2025Lake Victoria Gardens sidewalk ramps reconstruction   March 2025
Green Bike Lanes   April 2025Crosswalk installed at Fairchild Gardens Road   April 2025Installation of traffic loops   April 2025
 
 
Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone
zero