SR 9/I-95 at SR 786/PGA Boulevard Southbound Entrance Ramps Project
Financial Number: 4435901-1-52-01
Project Length: 0.65 miles
Project Limits: I-95 from PGA Boulevard to Burns Road
Start Date: November 2022
Completion Date: December 10, 2024
Contractor: UAG Construction
Estimated Construction Cost: $9,977,382
Virtual Public Meeting:
Scope of Work:
Work consists of reconfiguring the I-95 southbound entrance ramps at PGA Boulevard. The I-95 southbound entrance ramp from westbound PGA Boulevard to southbound I-95 will be converted from a merge lane to an additional, free-flowing lane. The I-95 southbound entrance ramp from eastbound PGA Boulevard to southbound I-95 will be reconfigured to create a merge lane. In addition, I-95 will be widened between PGA Boulevard and Burns Road, and lighting, drainage, signage and pavement markings will be upgraded.