Financial Number: 447671-1-52-01
Project Length: (0.608) miles
Project Limits:
- SR 704/Okeechobee Blvd from Red Trail to west of Australian Avenue
Virtual Public Workshop:
Anticipated Letting: July 2024
Anticipated Start: Fall 2024
Anticipated Completion: Summer 2025
Estimated Construction Cost: $2.3 million
Scope of Work:
- Repave and restripe the existing roadway within the project limits
- Replace sidewalk to remove trip hazards and correct slope to meet Americans with Disability Act (ADA) standards
- Upgrade pedestrian signalization and lighting at crosswalks
- Replace traffic detector loops and install traffic signal backplates
- Replace damaged drainage inlet tops
- Upgrade signage and Traffic Monitoring Site equipment
- Install Wrong Way Driving (WWD) Alert system.
Construction Impacts:
- Work will be performed in phases to reduce the effects of construction on the community
- Detours and temporary lane closures will occur during non-peak hours (8:30 PM to 6:30 AM) reducing impact to the traveling public
- Access to properties adjacent to the corridor will be maintained throughout construction
- Detours are necessary for ramp Wrong Way Driver installation
- Lane closures will be limited to one travel lane at a time