Financial Number: 449279-1-56-01
Project Length: 0.372 miles
Purpose of Project: The purpose of this lighting project is to improve the lighting conditions and meet
current FDOT lighting retrofit criteria at the following locations:
- Project Limits: SR 704/Okeechobee Boulevard both eastbound and westbound from Riverwalk Boulevard to North Jog Road
- Intersection 1: SR 704/Okeechobee Boulevard at Riverwalk Boulevard
- Intersection 2: SR 704/Okeechobee Boulevard at North Jog Road
Project Improvements:
- Replace existing luminaires on Florida Power and Light (FP&L) owned poles to ensure corridor lighting uniformity and it meets FDOT lighting criteria.
- The construction of this project will be completed by FP&L.
Construction Impacts:
- The MOT plan will be designed by FP&L.
- At least one access point to each adjacent property will be maintained throughout construction.
Public Meeting Workshop: No public information meeting is scheduled for this project.
Anticipated Construction Start and End Date: To Be Determined (TBD) by FP&L
Estimated Construction Cost: $151,709
Documents:
449279-1 Okeechobee Lighting Flyer - No Public Workshop_v2.pdf
Point of Contact:
Para información y preguntas en Español, por favor llame al (954) 777-4302.