Financial Number: 432066-8-52-01
Project Length: 1.5 miles
Project Limits: SR 817/University Drive from Riviera Boulevard to SR 824/Pembroke Road
Start Date: August 2022
Completion Date: Summer 2024
Contractor: OHLA USA, Inc.
Estimated Construction Cost: $11,281,680
Scope of Work:
The project improvements consist of: installing curb, gutter, and sidewalks; upgrading curb ramps, signing and pavement markings; constructing bus shelters at existing bus stop locations; adding a new pedestrian overpass bridge near the intersection of Miramar Boulevard, over the South Broward Drainage District (SBDD) Canal No. 1; upgrading pedestrian signals with countdown timers at the intersection of SR 817/University Drive and Miramar Parkway, SR 817/University Drive and Miramar Boulevard, SR 817/University Drive and Pembroke Road; replacing light poles and adding pedestrian lighting at the intersections of SR 817/University Drive and Riviera Boulevard, SR 817/University Drive and Miramar Parkway, SR 817/University Drive and Miramar Boulevard, SR 817/University Drive and Pembroke Road.
Point of Contact:
"Para información y preguntas en Español, por favor llame al (954) 777-4302."
Documents:
Project Flyer
|