State Road (SR) 7/US 441 at Oakes Road Intersection Improvements Project

Financial Number: 443591-1-52-01

Project Length: 0.327 miles

Project Limits: SR 7/US 441 at Oakes Road

Start Date: September 2023

Completion Date: Summer 2024

Contractor: Weekly Asphalt Paving, Inc.

Estimated Construction Cost: $2,144,350

Scope of work:

The project improvements consist of widening the eastbound approach on Oakes Road to provide dual left turn lanes and an exclusive right turn lane, striping 7-foot buffered bicycle lanes along southbound SR 7/US 441 between Oakes Road and south of the I-595 interchange, milling and resurfacing the roadway within the project limits, reconstructing existing sidewalks and curb ramps along Oakes Road, upgrading lighting, signing and pavement markings and upgrading the existing signalizations to mast arms.

Documents:

PDF IconProject Flyer

Point of Contact:

"Para información y preguntas en Español, por favor llame al (954) 777-4302."

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

During Construction

Oakes Rd. Strain Pole Removal February 2024 Oakes Rd. Median Concrete Pour   February 2024 Concrete pour   February 2024 Road widening   February 2024
Resurfacing operations – March 2024 Installation of Trees – March 2024
 




Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest