State Road (SR) 818/Griffin Road Resurfacing Project

Financial Number: 446371-1-52-01

Project Length: 2.5 miles

Project Limits: From SR 823/Flamingo Road to SW 90th Avenue

Start Date: January 2024

Completion Date: Early 2025

Contractor: Weekley Asphalt Paving, Inc.

Estimated Construction Cost: $4,434,510

Scope of Work:

The project improvements consist of: milling and resurfacing the roadway; upgrading existing lighting with LED fixtures within the project limits; upgrading pedestrian signalization at the intersections of SR 823/Flamingo Road, SW 118th Avenue, SW 106th Avenue, SW 100th/Palm Avenue; and upgrading pavement markings and signage.

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

Documents:

PDF IconE4W49 Griffin Road Resurfacing_Project Flyer

 

Project Photos

Pre Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details
Concrete Sidewalk Installation   January 2024Concrete Sidewalk and Inlet Top Installation   March 2024Light Pole Base Installation   March 2024completion of signalization   April 2024
Pull Box Apron Installation   April 2024Bullet Rail Installation   May 2024Handrail Installation May 2024
 
 
Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express