SR 817/University Drive from SR 84 To NW 1st Street Mobility Improvements Project
Financial Number: 432066-9-52-01, 02, 03
Project Length: 1.5 miles
Project Limits: SR 817/University Drive from SR 84 to NW 1st Street
Start Date: April 21, 2022
Construction Date: Summer 2023
Completion Date: Fall 2024
Contractor: General Asphalt Company, LLC
Estimated Construction Cost: $8,895,417
Scope of Work: Project improvements include widening the roadway to accommodate bicycle lanes in each direction; upgrading curb ramps, signage, and pavement markings; constructing bus shelters at existing bus stop locations; upgrading pedestrian signals with countdown timers at Peters Road, he Fountains Entrance, Federated Road, and SR 842/Broward Boulevard; and removing and replacing light poles impacted by widening operations.
Point of Contact:
Para información y preguntas en Español, por favor llame al (954) 777-4302.