Financial Number: 446185-1-52-01
Project Length: 2.387 Miles
Project Limits: State Road (SR) 5/US-1 (N. Federal Highway) from NE 17th Way to NE 33rd Court.
Start Date: June 16, 2022
Construction Start Date: Fall 2023
Anticipated Construction End Date: Spring 2025
Estimated Construction Cost: $5.4M
Scope of Work:
- Repave SR-5 / US-1 (North Federal Highway).
- Replace and upgrade existing pedestrian curb ramps to comply with Americans with Disabilities Act (ADA) standards.
- Upgrade Signing and markings to provide bike lanes.
- Extend US-1 northbound left turn lane at NE 26th Street Intersection.
- Replace traffic signals at Sunrise Boulevard, NE 13th Street and NE 26th Street intersections.
- Improve pedestrian signals and lighting at signalized intersections to meet current requirements.
Construction Impacts:
- Temporary lane closures on SR-5 / US-1 during off peak hours will be performed.
- Work will be completed in phases to minimize construction impacts.
- Access to adjacent properties will be maintained at all times.
Contact Information:
- Henry Oaikhena, P.E. — FDOT Project Manager
- Phone: (954) 777-4445 or Toll Free (866) 336-8435 Ext. 4445
- Email: [email protected]
|