FDOT District Four - Palm Beach Header Image

Districtwide Rumble Strips Improvements Project

Financial Number:452226-1-52-01

Project Length: 125 miles

Project Limits: Along multiple roadway corridors within cities located in Palm Beach and Broward Counties.

Virtual Public Meeting: N/A

In-Person Construction Open House: N/A

Start Date: June 3, 2024

Completion Date: Fall 2024

Contractor: Alexander Design + Build, LLC

Estimated Construction Cost: $654,155.45

Scope of Work:

  • The project improvements consist of adding rumble strips and replacing pavement markings in 13 different roadway corridors within Palm Beach and Broward Counties.

Documents:

PDF IconDistrictwide Rumble Strips_ Project Information Flyer.pdf

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

Project Map:



Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Districtwide Rumble Strips SR80

During Construction

SR 80_Rumble Strips Operation_July2024_SR 80_Rumble Strips Operation_July2024SR 7_Rumble Strips Installations_July2024SR 80_Rolling Rumble Strips Installations_July2024
SR 710_Beeline Hwy_Striping_June2024SR 7_Rumble Strips Installation July2024_SR 7_Arrowhead truck in Rolling Rumble Strips Installation_ Jul122024SR 80 Rumble Stips installation_July2024
SR 7_Rumble Stips Installation_July2024sinusoidal rumble strip gringind outer edge line_ SR 7_ Aug2024
 
Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone