FDOT District Four - Palm Beach Header Image

State Road (SR) 5/North Federal Highway Milling and Resurfacing Project

Financial Number: 446173-1-52-01

Project Length: 1.298 miles

Project Limits: State Road (SR) 5/North Federal Highway from south of 10th Avenue South to 6th Avenue North

Virtual Public Meeting:

Start Date: June 18, 2024

Completion Date: Spring 2025

Contractor: JW Cheatham LLC

Estimated Construction Cost: $2.3 million

Scope of Work: Project improvements consist of milling and resurfacing the existing roadway, adding drainage and constructing a raised intersection at 7th Avenue South, upgrading pedestrian curb ramps to meet Americans with Disabilities Act (ADA) standards, installing signalized pedestrian crossings with Rectangular Rapid Flashing Beacons (RRFBs) at 8th Avenue South, 3rd Avenue North, and 4th Avenue North, removing the existing midblock crossing between 4th Avenue North and 5th Avenue North, upgrading vehicular and pedestrian signalization at 6th Avenue South and 2nd Avenue North, installing lighting at the intersections of 8th Avenue South, 6th Avenue South, 2nd Avenue North, 3rd Avenue North, and 4th Avenue North, and upgrading signage and pavement markings for shared bicycle facilities and buffered bicycle lanes.

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

Documents

PDF IconLakeWorthBeachCoffeewithConstruction (1)_final

PDF IconProject Flyer

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

1

During Construction

Drainage work   July 2024concrete removal   July 2024SR 5 and 7th Ave S   August 2024Facing WB SR 5 and 6th Ave S   August 2024
milled, repaved and striped SR 5 and 7th Ave   August 2024Facing EB SR 5 just west of 7th Ave S   August 2024SB 7th Ave facing SR 5   August 2024final paving and striping b   September 2024
final paving and striping a   September 2024Drainage Pipe Installation  August 2024Road widening and new curb   August 2024Signalization and directional bore work   October 2024
Directional bore work   October 2024Directional bore work for signatlization   October 2024
 
Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone