Project Limits: From MP 12.599 in Palm Beach County to MP 25.854 south of the City of South Bay, Florida
Start Date: January 3, 2022
Completion Date: Fall 2024
Contractor: OHLA USA Inc.
Estimated Construction Cost: $18 Million
Scope of Work: Project improvements include widening the shoulders of the roadway, replacing, or resetting guardrails along the roadway, installing rumble strips and internally illuminated retroreflective pavement markings along the roadway shoulders, adding a median acceleration lane and flashing beacons at the Okeelanta Road intersection, adding outside and median acceleration lanes at the County Road 827/Bolles Canal Road intersection.