Financial Number:
432797-1-52-01
Project Length: 0.763 miles
Project Limits: I-595 corridor between SW 30th Avenue and Ravenswood Road
Start Date: March 31, 2014
Completion Date: September 5, 2014
Contractor: Dragados USA
Estimated Construction Cost: $329,900
Scope of Work: Project improvements included improving drainage facilities underneath the I-595 corridor between SW 30th Avenue and Ravenswood Road as necessary in order to alleviate flooding problems on the roads and properties in the City of Dania Beach.