Financial Number:
429740-1-52-01
Project Length: 0.228 miles
Project Limits: East of Interstate 95 to West of South Bryan Road
Start Date: March 16, 2015
Completion Date: July 2, 2015
Contractor: Arc Electric, Inc.
Estimated Construction Cost: $480,023.84
Scope of Work
The improvements under this project consisted of extending the left turn lane, replacing existing strain pole signal with mast arms, roadway lighting as well as removing old asphalt and repaving the roadway.
Click here for upcoming lane closures
|