Financial Number: 447664-1-52-01
Project Length: 3.342 miles
Project Limits: S.R. 15/E Main Street from Annona Street to south of S.R. 700/Conners Highway
Virtual Public Meeting: Thursday, October 16, 2025, from 5:00 p.m. to 6:00 p.m. Please use the following link to register: https://tinyurl.com/SR15EMAIN . You may also call +1 (213) 929-4212, Access Code: 547-912-812
In-Person Construction Open House: Thursday, October 16 2025, from 6:00 p.m. to 7:00 p.m. at the City of Pahokee— Pahokee Commission Chamber located at 360 E Main Street, Pahokee, Florida 33476
Start Date: November 3, 2025
Completion Date: Summer 2026
Contractor: General Asphalt
Construction Cost: $3.5 million
Scope of Work:The project improvements consist of milling and repaving the existing roadway within the project limits to ensure long-term infrastructure resiliency and safety, constructing five concrete bus pads throughout the project corridor to enhance transit rider safety and accessibility, installing curb ramps to enhance pedestrian safety and connectivity, and upgrading signage and pavement markings to enhance visibility and safety.
Point of Contact:
Para información y preguntas en Español, por favor llame al (954) 777-4302.