Financial Number: 439847-1-52-01, -02, and 436868-1-52-01
Project Length: 5.058 miles, with a 5-mile exception area between each project
Project Limits: US 1/SR 5, from south of SR 716 to Rio Mar Drive
US 1/SR 5 at SR 70
Start Date: November 19, 2020
Completion Date: May 3, 2022
Contractor: C.W. Roberts Contracting, Inc.
Estimated Construction Cost: $7,223,963.53
Scope of WorkThe improvements on the US
1/SR 5 project, from south of SR 716 to Rio Mar Drive include: milling and resurfacing the existing
roadway; restriping to provide 6‐foot buffered bicycle lanes; upgrading pedestrian signals, detectors
and lighting at signalized intersections; and upgrading sidewalk and curb ramps to meet Americans with
Disabilities Act (ADA) requirements.
The improvements on US 1/SR 5 at SR 70 include: widening the existing roadway in the NW corner of the
intersection to accommodate a southbound right-turn lane; relocating the existing Treasure Coast
Connector Plus bus stop shelter and its amenities; and installing ADA compliant curb ramps and
lighting improvements.