SR-656/17th Street East End of Bridge Rehabilitation and Improvements Project

Financial Number: 446106-2-52-01

Project Length: 4,730.5 Feet / 0.90 Miles

Project Limits:
From the west side to the east side of the SR-656/17th Street bridge

Virtual Public Meeting:

Start Date: September 5, 2023

Completion Date: Summer 2028

Contractor: Vecellio & Grogan, Inc.

Estimated Construction Cost: $22.3 million

Scope of Work: The project improvements consist of replacement of the eastern 400 feet of the existing bridge; sealing the full length of the existing bridge deck surface; and upgrading signing and pavement markings.

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

Documents:

PDF IconFULL CLOSURE 17th Street Bridge Dec. 9-13.pdf

PDF Icon17th Street Bridge Project Update January 2024

PDF IconVPM 17th Street Bridge

Click here for upcoming lane closures

 

Pre-Construction

Click to view enlarged version/details
During construction During construction During construction During construction

During Construction

Click to view enlarged version/details
During construction During construction During construction During construction
During construction During construction During construction During construction
During construction During construction
Driving of production piling completed at Bent 64, Mar. 2024Testpile at Bent 59, Mar. 2024
Relocation of floating pile template, Mar. 2024Backfilling of casings with sand, Mar. 2024Performing for Piling installation, Apr. 2024Receiving Piling Materials, Apr. 2024
Phase I piling installation completed, Apr. 2024Relocation of piling template, Apr. 2024Placing concrete phase 1 bent cap 59, May 2024Installing Pile formwork hangers, May 2024
Placing concrete phase 1 bent cap 59, May, 2024Setting beams span 56, July 2024FIBs set span 56, FSBs set spans 57 60, July 2024End bent 65 placed and cured, July 2024
Phase I FSB slabs in place for spans 60 62, July 2024Reinforcing stirrups tied and installed for Phase I FSB spans 57 60, Aug. 2024Concrete placed and curing Phase I Span 56, Aug. 2024Deck phase 1 prepared for barrier wall installation, Oct. 2024
Excavation for the subgrade and base for approach slab phase 1, Oct. 2024Setting type K barrier wall preparing for Phase 2 MOT transition, Nov. 2024Planning the Phase 1 deck riding surface, Nov. 2024Placing concrete Phase 1 approach slab, Nov. 2024

 

 

 

Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
zero