SW Port St. Lucie Boulevard Widening Project

Financial Number: 431752-6-52-01

Project Length: 0.713 miles

Project Limits: From south of SW Alcantarra Blvd. to south of SW Darwin Blvd.

Start Date: January 27, 2022

Completion Date: Early 2025

Contractor: Zahlene Enterprises, Inc.

Estimated Construction Cost: $11,570,179.20

Scope of Work:
Project improvements include widening SW Port St. Lucie Blvd. from a two-lane undivided roadway to a four-lane divided roadway, installing three new signalized intersections with mast arms at SW Alcantarra Blvd., SW Tulip Blvd., and SW Tunis Blvd., adding a right turn lane on SW Port St. Lucie Blvd.’s north approach to SW Alcantarra Blvd., constructing an 18’ wide raised median with curb and gutter, upgrading crosswalks and curb ramps to meet Americans with Disabilities Act (ADA) standards, constructing 8’-10’ wide sidewalks on both sides of SW Port St. Lucie Blvd. for pedestrian and bicycle use, and 6’ wide sidewalks on side streets, installing a new closed drainage system, signing, pavement markings, signalization, and lighting upgrades, and landscaping for the median including trees, irrigation and stamped concrete.

Point of Contact:

"Para información y preguntas en Español, por favor llame al (954) 777-4302."

Documents:

PDF IconVPM St. Lucie West Blvd

Click here for upcoming lane closures

 
 
 

Project Photos

Pre-Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details
1920
21 ZEI Canal Excavation, Feb. 2024 ZEI Compacting embankment within previously mass backfilled locations of watermain, Feb. 2024 Gerelco installing signalization components, Feb. 2024
Performing joint mast arm inspection, Mar. 2024 S 607 Headwall setting, Mar. 2024 Removing existing Asphalt on Tunis Avenue, Apr. 2024 Removing existing Force Main, left turn roadway just north of Alcantarra Blvd, Apr. 2024
Signal & lighting conduit at SW Tunis Ave, May 2024 Installing drainage on North Globe Avenue, May 2024 Installing curb and gutter on Alcantarra Blvd., May 2024 Installing Sod along the canal, May 2024
Placing concrete for signal cabinet foundation at Alcantarra Boulevard, June 2024 Grading final lift of base rock on Alcantarra Boulevard, June 2024 Subgrade thickness inspection behind redland, just south of S Globe Avenue, June 2024 Structural asphalt on Alcantarra Boulevard, July 2024
Placing concrete for new sidewalk, NE corner of Tunis Ave., July 2024 Subgrade work, just south of Trouville Ave., July 2024 Subcontractor extending the bored lighting conduits under SW Port St. Lucie Boulevard, Aug. 2024 Left turn roadway at PSL Blvd. and Alcantarra, paving temporary asphalt, September. 2024
Subcontractors removing existing signal heads at Tunis Avenue, September. 2024





Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone