Financial Number: 437717-1-52-01
Project Length: 0.180 Miles
Project Limits: CR 612/8th Street over Lateral Canal C Canal – MP 0.911 to MP 1.091
Public Meeting:The Public Meeting would be offered in two formats: virtual (online) and in-person. Both formats will take place at the same time.
Date: Tuesday, May 24, 2022, at 6:00 p.m. to 7:00 p.m.
Virtual Attendees: To participate in the virtual (online) Public Meeting from your computer, tablet, or smartphone, please register using: https://bit.ly/FDOT-CR612-publicmeeting. If you prefer to join by phone, please dial (213) 929-4212, Access Code: 434-482-354.
In-Person Location: Indian River County Administration Building B, 1800 27th Street. Vero Beach, FL 32960
The latest social distancing guidelines will be followed.
Projected Letting: February 2023
Start Date: Summer 2023
Completion Date: Summer 2024
Estimated Construction Cost: $3.9 Million
Scope of Work:
- Replacement of existing two-lane bridge over the Lateral canal C
- Dredging Lateral Canal C to accommodate the new bridge Construction
- Installation of guardrail to shield the canal hazards
- Reconstruction of the approaching roadways needed to connect to the new bridge
- Signing and Pavement Marking upgrades
Construction Impacts:
- Full closure of the CR 612/8th Street and 74th Avenue intersection is anticipated for the duration of construction. Detours will be provided.
Contact Information:
Documents: