Financial Number: 449281-1-52-01
Project Length: 0.583 miles
Project Limits: SR 9/I-95 northbound exit ramp to westbound SR 68/Orange Avenue
Virtual Public Workshop: None
Projected Letting: July 2025
Start Date: Winter 2025
Completion Date: Spring 2026
Estimated Construction Cost: $524 Thousand
Scope of Work:
- Milling and resurfacing existing roadway
- Overlay ramp with high friction surface treatment to improve safety
- Widen existing left shoulder from 2-feet paved to 4-feet paved
- Upgrade signing and pavement markings to enhance visibility
- Upgrade existing lighting to LED fixtures to improve visibility
Construction Impacts:
- Northbound to Westbound Ramp closures will be permitted as follows:
- Nighttime closure only, Sunday through Thursday, 8:00 a.m. to 6:00 a.m, for approximately 3 weeks.
- Detour using Northbound to Eastbound Ramp. Follow Jenkins Rd north to Loop Rd to turn back west. Approximate 1.25-mile route
- Additional information about lane closures, detours, and pedestrian impacts will be provided in the weekly traffic report distributed by FDOT at https://www.d4fdot.com/tcfdot/TC-Lucie_Closures.asp.
Contact Information:
Para información y preguntas en Español, por favor llame al (954) 777-4302.
Documents:
449281-1 - Flyer.pdf
|