Financial Number: 447555-1-52-01, 447555-2-52-01, 453333-3-52-01, 453333-2-52-01, 453333-1-52-01, 453333-4-52-01
Project Length: 17.745 miles
- FM 447555-1-52-01: 0.485 miles
- FM 447555-2-52-01: 0.356 miles
- FM 453333-3-52-01: 0.315 miles
- FM 453333-2-52-01: 9.812 miles
- FM 453333-1-52-01: 5.939 miles
- FM 453333-4-52-01: 0.838 miles
Project Limits:
- FM 447555-1-52-01: SR-710/SW WARFIELD BOULEVARD AT CR-714/SW MARTIN HIGHWAY
- FM 447555-2-52-01: SR-710/SW WARFIELD BLVD FR W OF SE 126 BLVD TO OKEECHOBEE/MARTIN CO LINE
- FM 453333-3-52-01: SR-710/SW WARFIELD BLVD FR W OF SE 126 BLVD TO OKEECHOBEE/MARTIN CO LINE
- FM 453333-2-52-01: SR-710 FROM MARTIN/OKEECHOBEE CO LINE TO FPL POWER PLANT ACCESS ROAD
- FM 453333-1-52-01: SR-710/SW WARFIELD BLVD FR FPL ACCESS RD TO SW ALLAPATTAH ROAD
- FM 453333-4-52-01: SR-710/SW WARFIELD BLVD FR SW ALLAPATTAH ROAD TO SW VAN BUREN AVE
Virtual Public Workshop: To Be Determined
Link to registration page (to be determined)
Projected Letting:
- FM 447555-1-52-01: 7/25/2029
- FM 447555-2-52-01: 7/25/2029
- FM 453333-3-52-01: 7/25/2029
- FM 453333-2-52-01: Anticipated November 2030
- FM 453333-1-52-01: Anticipated November 2030
- FM 453333-4-52-01: 7/25/2029
Start Date: To Be Determined
Completion Date: To Be Determined
Estimated Construction Cost: $221.3 M
- FM 447555-1-52-01: 5.1M
- FM 447555-2-52-01: 13.1M
- FM 453333-3-52-01: 2.3M
- FM 453333-2-52-01: 126.2M
- FM 453333-1-52-01: 62.5M
- FM 453333-4-52-01: 12.1M
Scope of Work:
FM 447555-1-52-01 and FM 447555-2-52-01
- Realignment of CR-714 to SE 126 Blvd
- New Signalization at SE 126 Blvd intersection
FM 453333-3-52-01
- SR-710 roadway widening with turn lanes at SE 126 Blvd intersection
- New
FM 453333-2-52-01 and FM 453333-1-52-01
- SR-710 conversion from 2 lane undivided roadway to a raised 4 lanes divided roadway with a median
- Separating shared ditches by providing independent roadway drainage ditches and irrigation ditches
- Shared Use Path along the northeast side of the road for pedestrian and cyclist use
- New Signage and Pavement Markings
- Overhead Utility Relocation
FM 453333-4-52-01
- Intersection improvements at SW Allapatah Rd. and Indianwood Dr. and new flashing signal at Martin County Fire Rescue - Station 24 east of SW Allapattah Rd.
- Shared Use Path along both sides of the Indiantown limits of SR-710
- Drainage improvements along the Indiantown limits of SR-710
Construction Impacts:
To be Determined
Documents:
Contact Information: