Financial Number: 439990-1-52-01
Project Length: 5.6 miles
Project Limits: Central Oakland Park and Harlem McBride Neighborhoods
Virtual Public Workshop: Tuesday, January 19, 2021 from 6:00 p.m. until 7:00 p.m.
Link to registration page:
https://attendee.gotowebinar.com/register/968656960379533326
Participants can also dial in using their phone:
+1 (562) 247-8421 Access Code: 127-649-039
Construction Start Date: Spring 2022
Anticipated Completion Date: Summer 2023
Estimated Construction Cost: $2 Million
Scope of Work:
- Construct sidewalks at various locations within the neighborhoods of Central Oakland Park and Harlem McBride.
- Relocate signs to meet the minimum horizontal sidewalk clearances to comply with the Americans with Disabilities Act (ADA) standards.
- Relocate impacted drainage structures.
- Regrade swales for proper drainage conveyance.