State Road (SR) 814/Atlantic Boulevard Resurfacing, Restoration, and Rehabilitation (RRR) Project
Financial Number: 449282-1-52-01 and 02
Project Length: 1 mile
Project Limits: SR 7/US 441 from NW 24th Street to Royal Palm Boulevard/West Copans Road and Royal Palm Boulevard/West Copans Road from NW 57th Terrace/East River Drive to SR 7/US 441
Project Information Video:
Start Date: March 2025
Completion Date: Fall 2025
Contractor: Weekley Asphalt Paving, Inc
Estimated Construction Cost: $2,850,117
Scope of Work: Project improvements consist of milling and resurfacing the existing roadway within the project limits to enhance long-term resilience; upgrading bus shelter pads along the project limits to enhance mobility; upgrading existing pedestrian signals at signalized intersections to improve push button accessibility; upgrading curb ramps, pavement markings, and signage to improve visibility and connectivity.