Floranada Road/Northeast 45th Street Sidewalk Connectivity Project

Financial Numbers: 441581-1-52-01 and 441581-1-52-02

Project Lengths: 0.975 miles

Project Limits: From State Road (S.R.) 818/Griffin Road to SW 14th Street

Start Date: Late January 2025

Completion Date: Late 2025

Contractor: Leon America Construction

Estimated Construction Cost: $1,950,676

Scope of Work: Project improvements consist of widening the S.R. 93/I-75 mainline to add an additional lane and enhance entry and exit movements; widening the S.R. 93/I-75 exit and entrance ramps at Royal Palm Boulevard and S.R. 818/Griffin Road to increase storage capacity and enhance traffic flow; widening the SR 93/I-75 bridge over the C-11 Canal to support the S.R. 93/I-75 mainline expansion and enhance traffic flow; installing Wrong-Way Driver Detection Systems at key locations to enhance safety: southbound S.R. 93/I-75 exit ramp to westbound Royal Palm Boulevard, northbound SR 93/I-75 exit ramp to westbound Royal Palm Boulevard, and northbound S.R. 93/I-75 exit ramp to westbound S.R. 818/Griffin Road; milling and resurfacing the roadway within the project limits to ensure long-term infrastructure resilience; upgrading signing and pavement markings within the project limits to enhance nighttime visibility; and upgrading existing light poles with new LED fixtures and installing additional poles throughout the project limits to enhance nighttime visibility.

Documents:

PDF IconWB Floranada Road Closure Flyer- Nov. 2025.pdf

PDF IconFloranada Sidewalk Connectivity Flyer.pdf

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Floranada Road Pre Construction 7 Floranada Road Pre Construction 5 Floranada Road Pre Construction 4 Floranada Road Pre Construction 1
Floranada Road Pre Construction 3 Floranada Road Pre Construction 2 Floranada Road Pre Construction 11 Floranada Road Pre Construction 10
Floranada Road Pre Construction 12 Floranada Road Pre Construction Floranada Road Pre Construction 9 Floranada Road Pre Construction 8

During Construction

Completed clearing and grubbing   February 2025Compacting material in preparation for proposed Concrete Sidewalk   March 2025Removing material in preparation for proposed concrete sidewalk   April 2025Installing Drainage Structure   May 2025
Installing Drainage Structure   May 2025 (2)Installing Drainage Structure   June 2025 (2)Installing Drainage Structure   June 2025Compacting backfill material around a drainage structure   July 2025

 

 




Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyMartin County Northern Palm Beach CountySt. Lucie County Western Palm Beach CountyIndian River County

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
95 Express
zero