Financial Numbers: 447680-1-52-01 and 447680-1-52-02
Project Lengths: 1.03 miles
Project Limits: From SR 820/Pines Boulevard to SR 824/Pembroke Road
Virtual Public Meeting: Thursday, January 16, 2025, from 5:00 p.m. to 6:00 p.m. Please use the following link to register: . You may also call +1 (415) 930-5321, access code: 471-184-147.
In-Person Construction Open House: Thursday, January 16, 2025, from 6:00 p.m. to 7:00 p.m. at the Charles F. Dodge City Center, 601 City Center Boulevard, Pembroke Pines, FL 33025.
Start Date: January 2025
Completion Date: Fall 2025
Contractor: Weekley Asphalt Paving, Inc.
Estimated Construction Cost: $3,165,008
Scope of Work: Project improvements consist of milling and resurfacing the existing roadway within the project limits to ensure long-term infrastructure resilience; constructing a right-turn lane along eastbound SR 824/Pembroke Road to southbound SR 823/Flamingo Road to improve vehicular capacity and mobility; replacing the traffic signal mast arm at the northeast corner of SR 824/Pembroke Road and
SR 823/Flamingo Road to enhance traffic safety and mobility, and improve signal visibility; upgrading existing pedestrian signals at signalized intersections to improve push button accessibility; upgrading concrete sidewalks, curb ramps, pavement markings, and signage to improve visibility and accessibility; and installing new light poles with LED fixtures at the intersections of Washington Street and SR 824/Pembroke Road to improve safety and enhance nighttime visibility.
Documents: 447674-1_Flamingo Road RRR_Project Flyer.pdf
Contact Information:
Para información y preguntas en Español, por favor llame al (954) 777-4302.
|