Financial Number: 434477-3-52-01
Project Length: 2.5 miles
Project Limits: I-75 from south of Miramar Parkway to north of Pines Boulevard, Miramar Parkway from SW 160 Avenue to SW 148 Avenue, and Pines Boulevard from SW 149 Avenue to SW 145 Avenue
Start Date: May 6, 2019
Completion Date: October 26, 2020
Contractor: Superior Landscaping & Lawn Services
Estimated Construction Cost: $2.5 million
Scope of Work: Project improvements include installing plants throughout the project limits, including several species of palms and shade trees and installing a temporary irrigation system.
I-75 Landscaping Improvements Project Flyer
|