Lauderdale Lakes Greenway Mobility Improvement Project from NW 31st Avenue to NW 29th Avenue

Financial Number: 440746-4-52-01

Project Length: 0.25-miles

Project Limits: Lauderdale Lakes Greenway from NW 31st Avenue to NW 29th Avenue

Start Date: November 8, 2021

Completion Date: Early 2023

Contractor: Weekley Asphalt Paving, Inc.

Estimated Construction Cost: $712,000

Scope of Work:

Work consists of constructing a 10-foot shared-use path along NW 39th Street to connect to the existing greenway. The project also includes installing decorative pedestrian lighting to increase visibility, irrigation and landscaping.

Point of Contact:

 

Documents:

PDF IconLauderdale Lakes Greenway Mobility Project Flyer

 

Project Photos

Pre-Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details
 
 
Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express