Financial Number: 443461-1-52-01
Project Length: 1.49 miles
Project Limits: SR-9/I-95 To/From Park & Ride Bridge No. 860601, 860628, 860600, 860638 and SR-842 to NB SR-9/I-95 Bridge No. 860598
Projected Letting: May 2022
Start Date: Fall 2022
Completion Date: Spring 2023
Estimated Construction Cost: $8.3 M
Scope of Work:
- Bridge painting with full removal and replacement of existing paint/coating on the existing steel bridge.
- Minor repairs to bridge drainage system.
Construction Impacts:
- Work will be done in phases to reduce the effects of construction on the community.
- Occasional single lane closures during construction.
- Two-way traffic and access to all property will be maintained at all times.
Contact Information:
|