Financial Number:
433997-1-52-01 & 433998-1-52-01
Project Length: 0.796 miles
Project Limits: Davie Boulevard from SW 17th Avenue to SW 19th Avenue in Fort Lauderdale and Griffin Road from 91st Avenue to west of 87th Avenue in Cooper City
Start Date: February 29, 2016
Completed Date: August 12, 2016
Contractor: Interstate Construction, LLC
Estimated Construction Cost: $447,523.08
Scope of Work
The improvements include wall rehabilitation activities such as water-blasting to remove the unsightly efflorescence, mildew growth, and anti-graffiti paint. Crews will also apply sealant and two layers of mold-preventative, breathable paint.
Sound Barrier Wall/Privacy Wall Improvements Project
|