FDOT District Four - Broward Header Image

State Road (SR) 25/US 27 from SR 818/Griffin Road (MP 7.0) to Truck Stop (MP 7.489)

Financial Number: 4441795-1-52-01

Project Length: 0.400 Miles

Project Limits: State Road (SR) 25/US 27 from SR 818/Griffin Road (MP 7.0) to Truck Stop (MP 7.489)

Start Date: Fall 2021

Completion Date: Spring 2022

Estimated Construction Cost: $607,107.00

Scope of Work:

  • Upgrading the existing lighting system to meet current standards
  • Removing existing light poles
  • Installing new light poles
  • Adjust impacted guardrails

Construction Impacts:

  • Daytime temporary lane closures during non-peak hours will occur
  • All work will be done in phases to reduce the impacts of construction to the community
  • No full roadway closures or detours will occur
  • Access to businesses and residential properties will be maintained at all times during construction

Contact Information:

Documents:

PDF IconState Road 25/US 27 from SR 818/Griffin Road to Truck Stop Flyer

 

Project Photos

Click to view enlarged version/details
 
 
Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express