Financial Number: 443845-1-52-01
Project Length: 1.0 Mile
Project Limits: From Commercial Boulevard to Bailey Road
Public Meeting: Thursday, October 21, 2021, from 6:00 p.m. to 7:00 p.m.
Projected Letting: March 2022
Start Date: May 2022
Completion Date: Fall 2024
Estimated Construction Cost: $2.2 Million
Scope of Work:
- Resurface and restripe roadway pavement.
- Upgrade and expand existing corridor lighting to LED luminaires.
- Upgrade pedestrian lighting at signalized intersection crosswalks.
- Upgrade pedestrian curb ramps to meet standards.
- Provide new signs and pavement markings.
- Minor drainage improvements.
Construction Impacts:
- Construction will be done in phases to reduce the effects of construction on the community.
- Local impacts such as events, holidays and peak seasons will be considered.
- Short-term lane closures will occur during non‐ peak hours on non-event days:
- Daytime: 9:00 a.m. to 4:00 p.m.
- Nighttime: 9:00 p.m. to 6:00 a.m.
- Access to businesses and residences will be maintained at all times.
Contact Information:
Documents:
443845-1 Project Notification Flyer - Website
|