Financial Number: 429576-5
Project Length: 0.80 miles
Project Limits: Copans Rd. from SR-7/US-441 to 49th Terrace
Hybrid Public Workshop: Thursday, August 26, 2021, 6:00 p.m.
Projected Letting: July 2023
Start Date: Winter 2023
Completion Date: Winter 2024
Estimated Construction Cost: $2.2 M
Scope of Work:
- Widen sidewalk to 8-10ft to provide for a separated bicycle/pedestrian facility
- Stripe sidewalk to provide for a 4-ft bike path
- Miscellaneous milling and resurfacing of the pavement
- Bus stop improvements
- Provide drainage improvements as a result of widened pavement
- Pedestrian signal modifications
Construction Impacts:
- Lane closures are planned
- Access for emergency responders and driveways will be maintained
- Pedestrian detours will be provided where sidewalk closures occur
Contact Information:
Documents:
SR 7 Mobility Improvements Hybrid Public Meeting Presentation
|