Financial Number: 429576-3-52-01
Project Length: 1.6 miles
Project Limits:
- SR 7/US 441 from Orange Dr. to Riverland Woods Park
- SR-838 Sunrise Boulevard from SR 7/US 441 to NW 31 Avenue.
Virtual Public Workshop: Held Thursday, April 26, 2023 from 5:00 p.m. – 7:00 p.m.
Projected Letting: July 2024
Start Date: August 2024
Completion Date: January 2024
Estimated Construction Cost: $3.5 M
Scope of Work:
- New sidewalk on the east side of SR-7 between Orange Drive and Oakes Road
- New shared-use path on the east side of SR-7 connecting.
- Oakes Road to Riverland Woods Park
- New shared-use path along the Sunrise Canal (C-12) from
- SR-7/US-441 to NW 31 Avenue
- Associated drainage, signal, lighting, curb ramps, and signing.
- and pavement marking improvements.
- New crosswalk with flashing beacon at NW 34 Avenue
Construction Impacts:
- This project does not anticipate traffic detours.
Contact Information:
Documents:
429576-3 445673-1 Public Information Flyer SR-7v9
|