Financial Number: 429576-3-52-01
Project Length: 2.6 miles
Project Limits:
- SR 7/US 441 from Orange Dr. to Riverland Woods Park
- SR-838 Sunrise Boulevard from SR 7/US 441 to NW 31 Avenue.
Virtual Public Workshop: September 6, 2023 from 5:00 p.m. – 7:00 p.m.
Project Letting: Februrary 2025
Start Date: May 2025
Completion Date: September 2026
Estimated Construction Cost: $3.5 M
Scope of Work:
- New sidewalk on the east side of SR-7 between Orange Drive and Oakes Road
- New shared-use path on the east side of SR-7 connecting Oakes Road to Riverland Woods Park
- New shared-use path along the Sunrise Canal (C-12) from SR-7/US-441 to NW 31 Avenue
- Associated drainage, signal, lighting, curb ramps, and signing and pavement marking improvements.
- New crosswalk with flashing beacon at NW 34 Avenue
Construction Impacts:
- This project does not anticipate traffic detours.