Financial Number: 441721-1-52-01
Project Length: 0.618 Miles
Project Limits: SR 838/Sunrise Blvd from SR 5/US-1/Searstown to E of NE 10th Ave
Public Meeting: Thursday, August 12, 2021 at 6:00 PM to 7:30 PM
Virtual Public Meeting: Wednesday, August 11, 2021, at 6:00 PM to 7:30 PM
Participants may register at:
Registration page: https://attendee.gotowebinar.com/register/8925903979137394446
or can join by phone by dialing in to +1 (951) 384-3421; Access code: 296-241-773
In-Person Public Meeting: Thursday, August 12, 2021, from 6:00 p.m. to 7:30 p.m. and will be held at: GALLERYone Doubletree Suites located at 2670 East Sunrise Boulevard, Fort Lauderdale, FL 33304. The latest social distancing guidelines will be followed.
Start Date: Spring 2022
Completion Date: Early 2023
Estimated Construction Cost: $1.5 Million
Scope of Work:
- Adding a third westbound left turn lane at SR 838/Sunrise Boulevard and SR 5/US-1/Searstown
- Upgrade signing and pavement markings
- Improving traffic signals
Construction Impacts:
- Work will be scheduled in phases to reduce effects of construction on the community
- Temporary lane closures will take place during non-peak hours to reduce impact to the public
- Access to businesses and private properties will be maintained at all times during construction
Contact Information:
Documents:
SR 838 Sunrise Blvd From SR 5 US-1 Seartown to E of NE 10th Ave Intersection improvement Project Flyer
|