Financial Number: 443462-1-52-01
Project Length: 0.147 miles
Project Limits: SR-870/Commercial Blvd. WB On Ramp to I-95 SB
Projected Letting: May 2022
Start Date: Fall 2022
Completion Date: Spring 2023
Estimated Construction Cost: $450,000
Scope of Work:
Bridge painting with full removal and replacement of existing paint/coating on the existing steel bridge.
- Work will be done in phases to reduce the effects of construction on the community.
- Occasional single lane closures during construction.
- Two-way traffic and access to all property will be maintained at all times.
Contact Information:
|