SR 9/I-95 from Gatlin Boulevard to St. Lucie West Boulevard Safety Improvements Project

Financial Number: 443847-1-52-01

Project Length: 3.2 miles

Project Limits:

  • SR 9/I-95 from Gatlin Boulevard to St. Lucie West Boulevard

Virtual Public Workshop: Thursday, April 14, 2022, (5 pm to 7 pm)

Projected Letting: December 2022

Start Date: Spring 2023

Completion Date: Fall 2024

Estimated Construction Cost: $6 M

Scope of Work

  • Extend I-95 on-ramp auxiliary lanes
  • Install a Dynamic Message Sign (DMS) south of Gatlin Blvd interchange to provide real time messages to drivers
  • Install roadway lighting between Gatlin Boulevard and Crosstown Parkway on I-95
  • Install new freeway guide signs
  • I-95 pavement resurfacing and cross-slopes correction
  • Install dynamic curve warning system north of Gatlin Boulevard interchange; system will provide warning to drivers of excessive speed and wet pavement conditions.

Construction Impacts:

  • Temporary lane closures during off peak hours will be performed
  • Village Parkway Dr. will be used as a detour route during night-time lane closures on Gatlin Blvd northbound on ramp to I-95
  • Eastbound St. Lucie Boulevard will be used as a detour route during night-time lane closures on westbound St. Lucie Boulevard southbound on ramp to I-95.
 

 

 

 

Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express