Financial Number: 444122-1-32-01 and 444122-4-32-01
Project Length: 27 miles
Project Limits: From west of US 27 (MP 18.873) to the Collier County Line (MP 45.341)
Virtual Public Workshop: Not Applicable
Projected Letting: February 2024
Start Date: Spring 2024
Completion Date: Fall 2025
Estimated Construction Cost: $64.1 M
Scope of Work:
- Mill and resurface the existing roadway pavement to extends its service life.
- Correct substandard roadway cross slopes to meet current standards.
- Construct outside guardrail to protect errant vehicles.
- Construct median guardrail to protect potential median crossover crashes.
Construction Impacts:
- Work will be done along I-75 Alligator Alley mainline and shoulders from just west of US 27 to the Collier County Line.
- Construction activities will be limited to 2-mile increments to minimize traffic impacts.
Contact Information:
Documents:
CAP1 Flyer
|