SR A1A Mobility Improvements Project

Financial Number: 441360-1-52-01

Project Length: 3.5 miles

Project Limits: SR A1A from Southern Town Limit of Hillsboro Beach to Southeast 3rd Street

Start Date: June 17, 2022

Completion Date: November 20, 2023

Contractor: Weekley Asphalt Paving, Inc.

Estimated Construction Cost: $6,377,643

Scope of Work: Project improvements include milling and resurfacing the existing travel lanes, widening the roadway to accommodate designated bike lanes, adding a sidewalk along the west side of the roadway between Opal Towers and SE 10th Street, upgrading existing mid-block pedestrian crossings with Rectangular Rapid Flashing Beacon Signs, raising the roadway elevation from 900 Hillsboro Mile to south of Le Baron Apartments.

Point of Contact:

"Para información y preguntas en Español, por favor llame al (954) 777-4302."

Documents:

PDF IconMeeting Invitation and Project Flyer

 

Project Photos

Pre Construction:

Click to view enlarged version/details

During Construction:

Click to view enlarged version/details
 
 
Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express
zero