Financial Number: 41473-1-52-01
Project Length: 351 feet
Project Limits: State Road (SR) 844 / 14th Street Causeway over the Intracoastal Waterway
Start Date: October 25, 2021
Completion Date: Spring 2022
Contractor: Seminole Equipment, Inc.
Estimated Construction Cost: $1.07 Million
Scope of Work:
Work consists of painting the steel and concrete portions of the SR 844 / 14th Street Causeway bascule bridge (Bridge No. 860060) over the Intracoastal Waterway and refurbishing the span locks and other mechanical components of the bridge.
Documents:
SR 844 14th Street Causeway Bridge Painting Project Presentation
|