Financial Number: 448405-1-52-01
Project Length: 1.009 miles
Project Limits:
SR A1A from Flamingo Avenue to south of Pine Avenue
Public Meeting: The public meeting will be offered in-person and virtually simultaneously on Tuesday, October 15, 2024, at 5:30 p.m. at the Lauderdale-By-The-Sea Town Hall located at 4501 North Ocean Drive, Lauderdale-By-The Sea, FL 33308.
To participate in the virtual public meeting from your computer, tablet or smartphone please register using the link: https://bit.ly/SRA1A-FlamingoAve-PineAve-PM.
Participants can also use their phone by dialing +1 (415) 655-0052; Access Code: 829-386-383.
Projected Letting: September 2025
Start Date: Spring 2026
Completion Date: Fall 2026
Estimated Construction Cost: $3.5 M
Scope of Work:
- Repave the existing roadway
- Improve pedestrian signals
- Upgrade curb ramps to comply with the Americans with Disabilities Act (ADA)
- Replace damaged sidewalks
- Upgrade signage and pavement markings
Construction Impacts:
- Temporary pedestrian detours may be required during construction
- Work will be done in phases to reduce the effects of construction on the community
- Access to properties adjacent to the corridor will be maintained throughout construction
Contact Information:
Para información y preguntas en Español, por favor llame al (954) 777-4302.
|